Sprint 154 Progress Summary

March 23rd - April 6th

Summary

 Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 153 comprising 16 points  - 

  • Partner and Community support
    –  Forum discussions
    –  Support for the Federal Agencies
    –  Community support
  • Finalize HIMSS Demo
    • Client look and feel
    • Test data/use case
    • Internal demo
  • X12 Audit 
    – Continue development
  • Infrastructure 

The team completed 17 points and ensured that all development related to the HIMSS demo including data/integration pieces were complete. The team also did an internal dry run for the HIMSS demo. The X12 auditing which was a lower priority this sprint will be continued in future sprints. Tickets related to X12 auditing development were moved to the backlog.

Burndown:

Sprint Themes and related tickets for Sprint 154:

Partner and Community Support

  • The team continued to support the community via the CONNECT forums.

CONNECT Development

  • Team completed development for HIMSS demo for Universal Client and CONNECT adapter components with FHIR integration demonstrating PD,QD,RD workflow between two gateway systems. 
    • Created conformance service for the Binary resource service. 
    • Created test data and finalized GUI updates
    • Prepared handout for HIMSS demo.
    • Completed an internal demo/dry run.
  • The team continued to work on the X12 auditing development.

JIRA Planning Board of Committed User Stories for Sprint 154: