Sprint 161 Progress Summary
June 29th- July 13th
Sprint 161 Themes
- Release 4.5 Preparation Tasks
- Complete release testing
- Address WAS issue with Cross Gateway Query Client
- Complete release documentation
- Release notes
- Finalization of design/requirements documents
- Testing summary report
- System Implementation and Administration Manual
- System Architecture Document
- Complete release testing
- Support Tasks
- Work with DoD on JBoss FIPS installation (PKCS11) testing
- Work with SCQC team on security scan validation
The team completed 27 points this sprint. Release testing was completed and issues discovered during testing were addressed. CONNECT 4.5 was released on 13th July.
Burndown:
Sprint Themes and related tickets for Sprint 161:
Release 4.5
- The team fixed couple of issues discovered during release testing and completed release documentation.
- CONNECT 4.5 was successfully released on July 13 2015.- See here for all information - /wiki/spaces/CONNECT4/pages/32374811
- Release Notes can be found here - /wiki/spaces/CONNECT4/pages/32374819
- Release binaries can be found here - /wiki/spaces/CONNECT4/pages/32374813
- CONNECT source code can be found here - /wiki/spaces/CONNECTWIKI/pages/10584104
- The team followed-up with SCQC team on the security scans findings report for the release.
JIRA Planning Board of Committed User Stories for Sprint 161: