Sprint 172 Progress Summary

Nov 30th - Dec 14th

Sprint status is excellent. Audit logging to a file was implemented. The team started work on the audit viewer which will be continued next sprint. The team continued to support the federal agencies and open source community.Sprint review summary presentation is here.

Burndown:

Sprint Themes and related tickets for Sprint 172:

Development:

  • Audit logging and viewer
  • Performance Testing
    • Updated the environment and completed initial test run for all services.
    • Results show that we meet the performance numbers for most services except X12- Need to follow-up on X12 services since the numbers were not met.

  • Executed and submitted tests for eHealth Exchange Product certification tests

Partner/Community Support:

  • CONN-1629 (DOD)
  • CONN-1628 (Community)

JIRA Planning Board of Committed User Stories for Sprint 172:

Related Files for Sprint 172:

 

Sprint 172 code tag

Common-Types source

CONNECT-Webservices source