Sprint 184 Progress Summary
May 16th - May 27th
Summary
Sprint status is excellent. The team completed migrating automated testing environment to WildFly and made updates to the regression suite. This included configuring and integrating JMX into the embedded WildFly server environment and validation. The team also made progress with the Hibernate upgrade and made updates to the CONNECT code to utilize Hibernate 5.1.Final . Testing will be done next sprint
Sprint review slides can be found here.
Burndown:
JIRA Planning Board of Completed User Stories for Sprint 184:
Related Files for Sprint 184:
Sprint 184 code tag
Common-Types source
CONNECT-Webservices source