Sprint 185 Progress Summary

May 27th - Jun 13th

Summary

Sprint status is excellent. The team began testing the Hibernate upgrade across all the application servers and made great progress. The CONNECT ear was tested successfully across the application servers. Issues were found with Admin GUI dependencies and will be addressed next sprint. The team also worked on the FIPS implementation/configuration on WildFly and documented analysis here -/wiki/spaces/CONNECTWIKI/pages/75038722

Sprint review slides can be found here.

Burndown:

JIRA Planning Board of Completed User Stories for Sprint 185:

Related Files for Sprint 185: 

Sprint 185 code tag 

Common-Types source