January 12th - January 26th
Executive Summary
Overall Summary
Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 149 comprising 25 points. Themes for the sprint included Partner and Community support
...
The team completed 28 points this sprint. The team released patch Release 4.4.1 as scheduled which included specification compliance bug fixes and a connection utility tool. The team also participated in the CONNECT Change Control board and Direct Connect-a-thon
Burndown:
Sprint Themes and related tickets for Sprint 149:
Partner and Community support
...
- Continued backlog grooming and prioritization
- Process improvement discussions
JIRA Planning Board of Committed User Stories for Sprint 149: