The team made good progress this sprint, but were unable to complete all the work initially planned for the sprint ie., the transformers for QD and RD. This was due to additional research required for incorporating the asynchronous logging into the code base and supporting the feature on all supported application servers. In addition new members onboarded to the product team, the leaning learning curve could have been the other contributing factor. However, overall great progress was made with this feature specifically related to asynchronous logging and the team will continue working on known issues in the upcoming sprints.
...