May 6th - May 19th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 12.5 points.
Proposed Themes:
- Continued testing for Java 6 and Java 7 support
- Testing on WebSphere
- Multi-spec identification for QD/RD
- Review design approach
- Begin development
- Continue working on the HealtheWay certification pilot test cases
- Other tasks
- Prepare for May 21st CONNECT User Group meeting
- Partner and Community Support
- Ongoing Custodial Agent duties
Prioritized JIRA Planning Board of Committed User Stories for Sprint 107
Related Files
- Sprint 107 planning notes - Notes about the work planned in s107. (Also includes work completed for s106)
- JIRA. See Sprint 107