The Product team pointed and prioritized the following themes and tasks for Sprint 100, comprising 43.5 points. The team pulled in an extra 1.5 points during the sprint and completed 45 of the 45 total points for this sprint.
Proposed Themes:
- Complete Release Testing
- Re-verification tests (performed on JDK 1.7 11)
- Interop tests
- GUI testing
- Prioritize and address issues as necessary for RC2/GA
...
- Work with ONC VLER Support on their IV&V Testing outcomes from the Beta tag
- Prioritize and address any issues per published procedure
- GATEWAY-3390 - Fails to run on IBM WebSphere Application Server V8.x – Open- Closed
- GATEWAY-3404 - CONNECT Consumer Preferences Profile GUI - Patient search throws exception - OpenClosed
- GATEWAY-3405 - CONNECT Deferred Queue Manager GUI - Process Queue and Search Queue functionality throws exception - OpenClosed
- GATEWAY-3406 - CONNECT Universal Client GUI - Attempts to access the deployed application throw exception - OpenClosed
- GATEWAY-3349 - Initialization of Hibernate framework throws java.lang.NullPointerException - OpenClosed
- Prioritize and address any issues per published procedure
- Smoke Test CONNECT 3.3.1.3 with JDK 1.7 11
- Begin Began work on HiMSS 2013 Interoperability Demo materials
...