Info |
---|
Sprint status was good. The team accomplished most of the thematic work defined for the sprintmade good progress on the themes. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 1311 points.
The team completed 7.5 points this sprint. 3 tickets totaling 4.5 points were moved out.
- Support the May 21st CONNECT User Group Meeting; George Washington University (CONN-442)
- Final testing ticket for Java 6 & Java 7 Support
- Testing on Solaris/ SPARC operating system (CONN-423)
- Multi-Specification Identification for QD/RD
- Complete development for responding messages (CONN-418 moved to next sprint)
- Begin development for initiating messages(CONN-443/CONN-444 made progress, but not completed - moved to next sprint)
- Run HealtheWay certification pilot test cases for a vendor gateway (CONN-392)
- Fix MTOM issue(CONN-427, ONN-431, CONN-433, CONN-434, CONN-435, CONN-436)
...
- Sprint 108 review notes|Sprint 108 Progress Summary^s108_review and s109_planning.ppt|||\- Notes about the work completed in s108. (Also includes work planned for s109)
- Sprint 108 planning notes - Notes about the work planned in s108. (Also includes work completed for s107)
- JIRA. See Sprint 108