Sprint Review + Planning | Monday March 25th | 10am - 12pm ET |
March 25th - April 7th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status is good. The team accomplished almost all of the thematic work defined for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 104 comprising 14 points. The team added 2 more points as part of CONN-355 and 1 ticket/point (CONN-334)was moved out from the sprint related to auditing. The team completed 9.5 of the 15 total points for this sprint.
- 4.1 Release Preparation
...