July 14th - July 28th

Executive Summary

Overall Status

The Product team prioritized the following themes and tasks for Sprint 136 comprising 20 points. During the sprint there was a ticket(, tickest (CONN-1256/CONN-12651268) that was  were pulled in to fix a known an issue with the sprint tag build and 1 ticket(CONN-1265) was pulled out to accommodate the new tickets(CONN-1256/CONN-1268). Sprint status is good and the team completed 18 points this sprint.  One ticket for 2 points remained at the end of the sprint and placed back into the backlog.  These themes included -   

...

3) X12 support (Continued Discussion to facilitate understandingdiscussion and review of requirements)

Burndown

Image Added

Sprint Themes and related tickets for Sprint

...

136:

Community Implementation support

  • Responded to forum posts - http://www.connectopensource.org/developer-resources/forums
  • Support VA with 4.2.2.1 upgrade upgrade 
  • Fix sprint 135 build issue (CONN-12321268)
    • Several meetings throughout the sprint both phone and email correspondence
    • Reviewed the values in VA UDDI file, researched and edited the values with the corrected entries
    • Worked through a separate UDDI entry with the implementation team, determined to be a Healtheway data issue
    • Helped work through a DR endpoint issue with one of their testing partners
    • Merlin Crypto package classes read their related properties files from the bundled Properties.jar library; not the "config/nhin" folder
    • Provided guidance on an IO error, helped to configure the correct URL with the correct port
    eHealth Exchange Product testing - Added test patient data to test files(CONN-1217)
    • An issue was discovered during the S135 build in embedded Glassfish. The issue was attributed to CONN-1256(Direct Config Namespace issue).
    • CONN-1256 was addressed and it also solved the build issue.

Next Release (4.4)

  • Admin GUI
    • Integrating Administrative GUI pages with the back end configuration  services 
      • Completed integrating the Direct configuration services for Trust Bundles Domain set uprelations(CONN-1200)
        • CONN-1264 added to backlog
      • Completed integrating the Direct services for Anchor set up(CONN-1201)
        • CONN-1266 will be addressed in S136
      • Completed integrating the Direct services for Certificates set up(CONN-1203)
        • CONN-1265 will be addressed in S136
      • Completed integrating the Direct services for Agent Settings set up(CONN-1204)
      • Completed integrating the Direct services for Trust Bundles set up(CONN-1205)
      • Fix Admin GUI sidebar UI/scrolling issues.(CONN-1216 and supporting tasks1202) that allows association of trust bundles to domains.
      • Completed integrating the Direct configuration services for Domain Address (CONN-1262) that allows for adding and deleting addresses
    • Fixed Miscellaneous UI issues with Admin GUI and branding (CONN-1257)
      • CONNECT Logo appears on Login page.
      • Utility nav bar at the top shows a full height (instead of short) border line at the leftmost side – might have to zoom in to see it.
      • Buttons on Gateway Dashboard line up properly.
      • In Internet Explorer 8, some text objects on the pages should adjust in size depending on browser window size.
    • Fixed UI issues for Manage Roles and User Management pages(CONN-1258)
    • Fixed UI issues on Direct config screens(CONN-1259)
      • On each Direct screen, all buttons are on the bottom of the tables.
      • The modal windows pop-up nearer to the top of the screen – to visually appear just under the utility nav bar at the top
    • Fixed Cert and Anchor uploads to only accept files with valid extensions(CONN-1261)
    • Fixed an issue related to deleting an anchor(CONN-1266)

  • Support for NwHIN CAQH Core X12 Document submission service
    • Continue to review specifications and other artifacts with the CMS team.
    • Received feedback and incorporate the feedback into the wiki and further discussions.
    • Continue to facilitate discussions with CMS

JIRA Planning Board of Committed User Stories for Sprint

...

136:

Image RemovedImage AddedImage Removed

Image Added

 

Related Files

Sprint 135 136 code tag