Tip

Sprint Review + Planning | Monday March 25th | 10am - 12pm ET
Tel: 646-216-4772 | 866-946-0485 | Access Code: 922 914 63
Web Meeting (Meeting Number: 145 254 634)
Add to your calendar

March 25th - April 7th, 2013

Executive Summary

Overall Status

Info

Sprint status is good. The team accomplished almost all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 104 comprising 14  points. The team completed XX of the 14 added 2 more points as part of CONN-355 and 1 ticket/point (CONN-334)was moved out from the sprint related to auditing. The team completed 9.5 of the 15 total points for this sprint.

...

  • Incorporate CI Testing Improvements to Additional App Servers (not completed in Sprint 104)
  • Start Work on Design for Enhancements to Auditing
  • Completed questionnaire for HIE Certified Network 
  • Resolved Support tickets

Prioritized JIRA Planning Board of Committed User Stories for Sprint 104 