Aug 11th - Aug 25th
Executive Summary
Overall Status
...
Sprint status is excellent and the team completed 30 points this sprint, one ticket that was created in anticipation for VA support was not included completed since there were no support needs. The team completed the X12 Document Submission framework for the real time transactions transactions, including a draft design this sprint.
...
JIRA Planning Board of Committed User Stories for Sprint 138:
Related Files
Sprint 138 code 138 code tag