Sprint Review + Planning | May 20th | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

May 20th - Jun 3rd, 2013

Executive Summary

Overall Status

Info

Sprint status was good. The team made good progress on the themes identified for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 11  points.

The team completed 7.5 points this sprint. 3 tickets totaling 4.5 points were moved out. 

...

Prioritized JIRA Planning Board of Committed User Stories for Sprint 108

Image RemovedImage Added

Related Files

  • Sprint 108 review notes|Sprint 108 Progress Summary^s108_review and s109_planning.ppt|||\- Notes about the work completed in s108. (Also includes work planned for s109)
  • Sprint 108 planning notes - Notes about the work planned in s108. (Also includes work completed for s107)
  • Sprint 108 code tag
  • JIRA. See Sprint 108