Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

October 20th - November 3rd

Executive Summary

Overall Status

Sprint status was good. The Product Team has prioritized the following themes and tasks for Sprint 142 143 comprising 34 36 points.  These themes included -   

  • Partner and Community support
    • Forum discussions
    • VA 4.2.2.2 implementation
    • SSA 4.3.2 implementation
    • DoD implementation questions
    • Community and OHT support
  • Direct (End to End Feature Testing, Bug Fixes, Setup for External HISP Testing)
  • Admin GUI (End to End Feature Testing,  Cleanup  and Bug Tickets, WebSphere Issue CONN-1291)
  • X12 (Continued Internal & Coordinated CMS Testing)
  • Begin 4.4 Release Preparation (Documentation)
  • Healtheway Product Certification Support (Research and Support for Vendor Reported Issues)

 

The team completed 42 points this sprint. Three tickets(6 points) could not be completed due to testing dependencies and will be looked at in the next sprint. The team added tickets into the sprint related to the Fortify scan findings and addressed all Critical, High and Medium issues found. Also, all Low Category 1 tickets were addressed. The team completed executing Direct test cases on GlassFish and validated Direct functionality. The other application servers will be tested next sprint for Direct. The team also worked on a POC related to an issue found on WAS that was preventing Direct configuration using the Admin GUI. This issue was addressed and will be tested in depth in next sprint.
The team also started with release preparation tasks for Release 4.4.

...