Jul 25th - Aug 8th
Summary
Sprint status is excellent. The team addressed all remaining SonarQube critical and blocker findings. All remaining issues related to the Hibernate upgrade were fixed. OWASP ZAP 2.5 has been set up, AdminGUI has been scanned and the team has started addressing the findings. The CONNECT 4.7 release test plan has been created. The team has completed QA of the Connectopensource.org migration. CONNECT 4.7 RC1 has been cut.
Sprint review slides can be found here.
Burndown:
JIRA Planning Board of Completed User Stories for Sprint 189:
Related Files for Sprint 189:
Sprint 189 (CONNECT 4.7 RC1) code tag
Common-Types source
CONNECT-Webservices source