Sprint Review + Planning | May 20th | 10am - 12pm ET
Registration for webinar: Click link below to register, and receive dial-in and Web participation details:
https://attendee.gotowebinar.com/register/7556627107749161728
May 20th - Jun 3rd, 2013
Executive Summary
Overall Status
Sprint status was good. The team accomplished most of the thematic work defined for the sprint.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 13.5 points.
- Support the May 21st CONNECT User Group Meeting; George Washington University (CONN-442)
- Final testing ticket for Java 6 & Java 7 Support
- Testing on Solaris/ SPARC operating system (CONN-423)
- Multi-Specification Identification for QD/RD
- Complete development for responding messages (CONN-443 moved to next sprint)
- Begin development for initiating messages(CONN-443 made progress, but not completed - moved to next sprint)
- Run HealtheWay certification pilot test cases for a vendor gateway (CONN-392)
- Fix MTOM issue
Prioritized JIRA Planning Board of Committed User Stories for Sprint 108
Related Files
- Sprint 108 review notes|Sprint 108 Progress Summary^s108_review and s109_planning.ppt|\- Notes about the work completed in s108. (Also includes work planned for s109)
- Sprint 108 planning notes - Notes about the work planned in s108. (Also includes work completed for s107)
- JIRA. See Sprint 108