December 1st - December 15th

Executive Summary

Overall Summary

Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 146.Themes for the sprint included -

The team completed 31 points during the sprint and released CONNECT 4.4 on time as scheduled. The team also presented a demo of the features and functions to the federal partners that was well received.

Burndown:

Sprint Themes and related tickets for Sprint 146:

Partner and Community support

Release 4.4 made generally available on Dec 9 2014 and documentation on the wiki was reviewed. The team also demo'd the new features available to the federal partners.

Support for NwHIN CAQH Core X12 Document submission service (Feature complete)

X12 Document Submission service documentation

System Administration Module or Admin GUI (Feature complete)

System Administration Module or Admin GUI documentation

Direct enhancements (Feature complete)

Direct documentation

 

Other tasks post release

JIRA Planning Board of Committed User Stories for Sprint 146: