March 9th - March 23rd
Summary
Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 153 comprising 31 points -
- Partner and Community support
– Forum discussions
– Support for the Federal Agencies
– Community support - HIMSS Demo
- Client front end design/UI mockup and branding
- Service architecture
- Implementing services
- Demo script with data loading/test data
- X12 Audit
– Begin development
The team completed 31 points, 2 tickets were pulled in later during the sprint and will be looked at next sprint. The team has the HIMSS demo components complete, and will continue to work on integration and data for the demo in the upcoming sprint.
Burndown:
Sprint Themes and related tickets for Sprint 153:
Partner and Community Support
- The team continued to support the community via the CONNECT forum.
- The team discussed the hl7 attribute scoping issue at the spec factory and is looking for guidance/direction on the specification interpretation and implementation. The CONNECT team was asked to validate whether CONNECT supports both qualified and unqualified versions of the attribute as the Responding gateway. Created CONN-1602 for validation.
- The team provided some initial feedback and further questions regarding issue that was brought up by CMS related to gateway-adapter and payloads. It is not clear at this point whether there is an issue at the gateway. The team has asked CMS for more information and to create a ticket with the relevant logs.
CONNECT Development
JIRA Planning Board of Committed User Stories for Sprint 153:
Related Files for Sprint 153:
Sprint 153 code tag
Common-Types source
CONNECT-Webservices source