March 23rd - April 6th

Summary

 Sprint status is excellent. The Product Team had prioritized the following themes and tasks for Sprint 153 comprising 16 points  - 

The team completed 17 points and ensured that all development related to the HIMSS demo including data/integration pieces were complete. The team also did an internal dry run for the HIMSS demo. The X12 auditing which was a lower priority this sprint will be continued in future sprints. Tickets related to X12 auditing development were moved to the backlog.

Burndown:

Sprint Themes and related tickets for Sprint 154:

Partner and Community Support

CONNECT Development

JIRA Planning Board of Committed User Stories for Sprint 154:

Related Files for Sprint 154:

Sprint 154 code tag

Common-Types source

CONNECT-Webservices source