Jan 25th - Feb 8th

Sprint status is excellent. The team made progress on security scans fixes and mitigation for Fortify/SonarQube found issues. The team fixed some of the remainder bugs for audit logging. The team also participated in the FHA Managing Board and provided the federal agencies an update on CONNECT 4.6.   For sprint review summary and themes for next sprint, presentation slides are here.

Burndown:

Sprint Themes and related tickets for Sprint 176:

JIRA Planning Board of Completed User Stories for Sprint 176:

Related Files for Sprint 176:

Sprint 176 code tag 

Common-Types source

CONNECT-Webservices source