Summary

Sprint status is good. CONNECT 5.0 RC1 was created. Release testing mostly completed with performance testing to be completed early next sprint. Release documentation also mostly completed and will be completed next sprint. The Fortify scan report was created and reviewed and is ready to be presented to the DoD SCQC team.