Sprint 115 Progress Summary

Sprint Review + Planning | Aug 26th | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

Aug 26 - Sep 09, 2013

Executive Summary

Overall Status

Sprint status is Excellent. The team accomplished all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

  • Wrap up next step in testing automation improvements
    • Finish Regression suite Framework for automation 
    • Next components of Testing Configuration management via JMX (i.e. Standard/ Entity)
    • Interoperability/integration test cases updates and enhancements
  • Continue supporting Healtheway/ CCHIT and community members on certification program  
    • Beginning to field support questions for community members actively engaged in certification testing
  • Support community with Release 4.2 deployments
  • Design Approach for Auditing enhancements 

Prioritized JIRA Planning Board of Committed User Stories for Sprint 115

(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)