Sprint 110 Progress Summary

Sprint Review + Planning | Jun 17th | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

Jun 17th - Jul 1st, 2013

Executive Summary

Overall Status

Sprint status is good. The team accomplished all of the thematic work defined for the sprint.

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 110 comprising 16 points. The team completed 15 points.

Burndown

Cumulative Flow

Sprint Themes

  • Multi-Specification Identification for QD/RD
    • Complete any remaining QA for both responding and initiating Multi-specification identification. (CONN-437, CONN-455)
  • Ensure all unit testing from Pilot and Feature tickets are incorporated into regression and validation suites
  • Release 4.2 testing plan dicussions and begin setting up necessary infrastructure (CONN-476)
  • Continue working with Healtheway certification test cases (Table 2) and address any findings (CONN-472, CONN-394,CONN-395, CONN-396)
  • Continue working on CI tickets and automated testing improvements (CONN-473,CONN-363,CONN-358)

Prioritized JIRA Planning Board of Committed User Stories for Sprint 110

(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)