Executive Summary
Overall Status
Sprint status is good. The team accomplished all of the thematic work defined for the sprint.
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 110 comprising 16 points. The team completed 15 points.
Burndown
Cumulative Flow
Sprint Themes
- Multi-Specification Identification for QD/RD
- Complete any remaining QA for both responding and initiating Multi-specification identification. (CONN-437, CONN-455)
- Ensure all unit testing from Pilot and Feature tickets are incorporated into regression and validation suites
- Release 4.2 testing plan dicussions and begin setting up necessary infrastructure (CONN-476)
- Continue working with Healtheway certification test cases (Table 2) and address any findings (CONN-472, CONN-394,CONN-395, CONN-396)
- Continue working on CI tickets and automated testing improvements (CONN-473,CONN-363,CONN-358)
Prioritized JIRA Planning Board of Committed User Stories for Sprint 110
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 110 review notes - Notes about the work completed in s110. (Also includes work planned for s111)
- Sprint 110 planning notes - Notes about the work planned in s110. (Also includes work completed for s109)
- Sprint 110 code tag
- JIRA. See Sprint 110
, multiple selections available,