Executive Summary
Overall Status
Sprint status is Excellent. The team accomplished all of the thematic work defined for the sprint and the release.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 113 comprising 24.5 points.
Proposed Themes:
- Rerun all Release 4.2 Testing on new GA build (CONN-461,CONN-555,CONN-557)
- Release 4.2 Regression Testing - https://developer.connectopensource.org/x/mgBnC
- Release 4.2 Installation Testing -https://developer.connectopensource.org/x/mABnC
- Release 4.2 Interoperability Testing -https://developer.connectopensource.org/x/EYC6C
- The Release 4.2 Testing Wiki page: https://developer.connectopensource.org/x/HgBgC
- The Release 4.2 Testing Summary Wiki page: https://developer.connectopensource.org/x/nABnC
- The Release 4.2 Interoperability Testing/Plan page: https://developer.connectopensource.org/x/BQCYC
- Complete Release 4.2 documentation (CONN-503)
- Release 4.2 – Support for JAVA 1.6 (CONN-350)
- The JAVA 1.6 Support Design Approach: https://developer.connectopensource.org/x/CQArC
- Release 4.2 – Multiple specification version enhancement support (CONN- 15 & CONN-46)
- Enhancing multi-spec support (initiating) Design Approach: https://developer.connectopensource.org/x/GoA0C
- Enhancing multi-spec support (responding) Design Approach: https://developer.connectopensource.org/x/kYDvBw
- Release 4.2 – Support for JAVA 1.6 (CONN-350)
- Healtheway Participation Certification Support
- Table 1 - https://developer.connectopensource.org/x/JwA4C
- Table 2 - https://developer.connectopensource.org/x/IoA7C
- Certification - https://developer.connectopensource.org/x/ZIC6C
- Final release preparation tasks for Release 4.2 availability (CONN-463)
Prioritized JIRA Planning Board of Committed User Stories for Sprint 113
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 113 review notes - Notes about the work completed in s113. (Also includes work planned for s114)
- Sprint 113 planning notes - Notes about the work planned in s113. (Also includes work completed in s112)
- JIRA. See Sprint 113
- Release 4.2 code tag
, multiple selections available,