Sprint 102 Progress Summary

February 25 - March 10, 2013

Executive Summary

Overall Status

Sprint status is Excellent. The team accomplished almost all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 102 comprising 20 points.  The reduced predicted velocity is due to team member attendance at HIMSS.
The team pulled in an extra 3 points during the sprint and completed 21.5 of the 23 total points for this sprint.

Prioritized JIRA Planning Board of Committed User Stories for Sprint 102

(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)

Related Files