Sprint 114 Progress Summary
Sprint 114 Progress Summary
Sprint Review + Planning | Aug 12th | 10am - 12pm ET
Registration for webinar: Click link below to register, and receive dial-in and Web participation details:
https://attendee.gotowebinar.com/register/7556627107749161728
Aug 12 - Aug 26, 2013
Executive Summary
Overall Status
Sprint status is Excellent. The team accomplished almost all of the thematic work defined for the sprint.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 14 points. The team completed 13 points.
- Next steps in CI and testing automation improvements
- Add JBoss to the automated CI process (CONN-490)
- Validation suite automatically runs at code check in
- Build Regression suite Framework for automation
- CONN-491, CONN-492, CONN-535
- Configuration management via JMX (i.e. Standard/ Entity)
- CONN-490
- Interoperability/integration test cases updates and enhancements
- CONN-563, CONN-567, CONN-568, CONN-569, CONN-570
- Add JBoss to the automated CI process (CONN-490)
- Continue working with Healtheway/ CCHIT on certification program
- Auditing enhancements
- CONN-573
- Support community that have begun Healtheway/ CCHIT participant certification testing
- Beginning to field support questions for community members actively engaged in certification testing
- Support community with Release 4.2 deployments
Prioritized JIRA Planning Board of Committed User Stories for Sprint 114
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 114 review notes - Notes about the work completed in s114. (Also includes work planned for s115)
- Sprint 114 planning notes - Notes about the work planned in s114. (Also includes work completed for s113)
- JIRA. See Sprint 114
- Sprint 114 code tag
, multiple selections available,