March 11th - March 24th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status is Excellent. The team accomplished almost all of the thematic work defined for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 24 23 points.
Proposed Themes:
- 4.0 Partner and Community Support
- SSA 4.0 install on WAS
- CMS-CCSQ 4.0 install on WL 11g or 12c
- CMS-OFM 4.0 install on WAS 7 JDK 1.7
- Respond to IHS re the Direct ticket (CONN-279)
- Community support through forum responses and guidance
...