March 11th - March 24th, 2013
Executive Summary
Overall Status
Sprint status is Excellent. The team accomplished almost all of the thematic work defined for the sprint.
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 103 comprising 23 points.
Proposed Themes:
- 4.0 Partner and Community Support
- SSA 4.0 install on WAS
- CMS-CCSQ 4.0 install on WL 11g or 12c
- CMS-OFM 4.0 install on WAS 7 JDK 1.7
- Respond to IHS re the Direct ticket (CONN-279)
- Community support through forum responses and guidance
- 4.1 Enhancements
- Multi-Spec QD / RD End point enhancement for DoD/SSA (pending DE&I approval)
- Installation improvements through community engagement
- Continued development of a robust CI and automated test environment
- JBoss - (CONN-25) in the Ordered features list
- 4.0.1 Patch Release - patch release test and make enhancements to 4.0 available to community
Prioritized JIRA Planning Board of Committed User Stories for Sprint 102
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 103 planning notes - Notes about the work planned in s103. (Also includes work completed for s102)
- JIRA. See Sprint 103