April 8th - April 21st, 2013

Executive Summary

Overall Status

Info

Sprint status is good. The team encountered some unplanned infrastructure maintenance that impacted completion of all themes identified for the sprint.

Burndown

Image Added

Cumulative Flow

Image Added

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 105 comprising 15.5 points. 0.5 points were added(CONN-367) and 3 points(CONN-317) were moved out as the team had to address some infrastructure maintenance tasks that were higher priority. The points committed were 13. The team completed 8 out of the total 13 points committed for the sprint.

  • 4.1 Release
    • Binaries and source available
    • Complete and finalize supporting documentation

...