The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points to the sprint with a total of 13.5 points. The team completed 13 points
- Continued Testing for Java 6 & Java 7 Support
- Installation testing on WL 11g / JDK 1.6 (CONN-383/CONN-384)
- Installation testing on WL 12c / JDK 1.7 (CONN-371)
- Installation testing on WAS 8.5 /IBM SDK 1.7 (CONN-370)
- Installation testing on JBoss 7.1.1 /JDK 1.7 (CONN-368)
- Installation testing on GlassFish 3.1.2 /JDK 1.7 (CONN-369)
- Smoke test on all installations
- Documentation (CONN-375)
- Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
- Review Responding design approach with technical leads from Federal Partners (conference call)
- Initiating design approach -
- HealtheWay certification pilot testing (system set up and smoke tests)
- CONN-317 Pre-test and smoke test for pilot
...