Sprint 106 Progress Summary

Sprint Review + Planning | April 22th | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

April 22th - May 5th, 2013

Executive Summary

Overall Status

Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points to the sprint with a total of 13.5 points. The team completed 13 points

  • Continued Testing for Java 6 & Java 7 Support
    • Installation testing on WL 11g / JDK 1.6 (CONN-383/CONN-384)
    • Installation testing on WL 12c / JDK 1.7 (CONN-371)
    • Installation testing on WAS 8.5 /IBM SDK 1.7 (CONN-370)
    • Installation testing on JBoss 7.1.1 /JDK 1.7 (CONN-368)
    • Installation testing on GlassFish 3.1.2 /JDK 1.7 (CONN-369)
    • Smoke test on all installations
    • Documentation (CONN-375) 
  • Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
  • HealtheWay certification pilot testing (system set up and smoke tests)