Sprint 117 Progress Summary
Sprint 117 Progress Summary
Sprint Review + Planning | Sep 23rd | 10am - 12pm ET
Registration for webinar: Click link below to register, and receive dial-in and Web participation details:
https://attendee.gotowebinar.com/register/7556627107749161728
Sep 23 - Oct 7, 2013
Executive Summary
Overall Status
Sprint status is excellent. The Product team completed 19 out of the 21 story points this sprint.
Burndown
Sprint Themes:
- Support community with Release 4.2 deployments
- Several active community installations underway
- Supported CMS with their 4.2 esMD installation(CONN-605,CONN-606)
- Begin Direct Updates
- Document and validate requirements for QoS and Trust Bundles (CONN-607)
- Install the current version of RI in our development env.(CONN-608)
- Finalize Audit Design Approach (CONN-334)
- Regression automation(CONN-583,CONN-610, CONN-625)
- Start deeper research of potential issues identified in the Fortify security scan results(CONN-611 -- not completed)
- Community Tickets
- CONN-340
Prioritized JIRA Planning Board of Committed User Stories for Sprint 117
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 117 planning notes\- Notes about the work planned in s117. (Also includes work completed for s116)
- Sprint 117 code tag
, multiple selections available,