Sprint 111 Progress Summary

Sprint Review + Planning | Jul 1st | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

Jul 1st - Jul 15th, 2013

Executive Summary

Overall Status

Sprint status is good. The team accomplished all of the thematic work defined for the sprint.

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 111 comprising 11 points.

Burndown

Cumulative Flow

Proposed Themes:

  • Finalize Release 4.2 Test Plan
  • Work on Testing Infrastructure
    • Interoperability lab environments
    • Install testing space
  • Begin Release 4.2 Testing
    • Installation testing
      • Binary and source installs (CONN-475,486, 494 & 497)
    • Interoperability testing
    • Regression testing
      • CONN-462, 483 & 510
    • Adapter Update to Support Testing 
      • Multiple event codes for Query for Documents (CONN-478)
  • Completed the Healtheway Pilot 
    • Including some rerun of updated test cases
  • Continued working on additional test cases for Healtheway certification (CONN-496)

Prioritized JIRA Planning Board of Committed User Stories for Sprint 111

(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)