Executive Summary
Overall Status
Sprint status is good. The team accomplished all of the thematic work defined for the sprint.
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 111 comprising 11 points.
Burndown
Cumulative Flow
Proposed Themes:
- Finalize Release 4.2 Test Plan
- Interoperability updates to Test Plan (CONN-485)
- Final general edits and review to Release 4.2 Test Plan
- Release 4.2 Testing Wiki page: https://developer.connectopensource.org/display/CONNECT4/4.2+Release+Testing
- Work on Testing Infrastructure
- Interoperability lab environments
- Install testing space
- Begin Release 4.2 Testing
- Installation testing
- Binary and source installs (CONN-475,486, 494 & 497)
- Interoperability testing
- Regression testing
- CONN-462, 483 & 510
- Adapter Update to Support Testing
- Multiple event codes for Query for Documents (CONN-478)
- Installation testing
- Completed the Healtheway Pilot
- Including some rerun of updated test cases
- Continued working on additional test cases for Healtheway certification (CONN-496)
Prioritized JIRA Planning Board of Committed User Stories for Sprint 111
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 111 review notes - Notes about the work completed in s111. (Also includes work planned for s112)
- Sprint 111 planning notes - Notes about the work planned in s111. (Also includes work completed for s110)
- Sprint 111 code tag
- JIRA. See Sprint 111
, multiple selections available,