Sprint 109 Progress Summary

Sprint Review + Planning | Jun 3rd | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

Jun 3rd - Jun 17th, 2013

Executive Summary

Overall Status

Sprint status was great. The team completed all the thematic work identified for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team started off with 16 points, but added a few more tickets to the sprint bringing the point total to 20 points that were completed. The team moved one ticket out of the sprint as we needed more information from the community. The team prioritized the following themes and tasks for Sprint 109.

Sprint Themes:

  • Multi-specification version identification for QD/RD
    • CONN-443, CONN-444, CONN-418, CONN-376, CONN-377, CONN-373, CONN-374
  • Complete final tickets for MTOM/XOP
    • CONN-408 and supporting testing ticke/validation tickets
  • Determine release test approach and draft 4.2 test plan 
    • CONN-457
  • Run any remaining HealtheWay certification pilot test cases when made publicly available
    • CONN-450, CONN-351, CONN-471
    • CONN 408 and CONN-440

Prioritized JIRA Planning Board of Committed User Stories for Sprint 109 <<TO BE UPDATED>>