Jul 1st - Jul 15th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status is good. The team accomplished all of the thematic work defined for the sprint. |
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 111 comprising 11 points.
Burndown
Cumulative Flow
Proposed Themes:
- Finalize Release 4.2 Test Plan
- Interoperability updates to Test Plan (CONN-485)
- Final general edits and review to Release 4.2 Test Plan
- Release 4.2 Testing Wiki page: https://developer.connectopensource.org/display/CONNECT4/4.2+Release+Testing
- Work on Testing Infrastructure
- Interoperability lab environments
- Install testing space
- Begin Release 4.2 Testing
- Installation testing
- Binary and source installs (CONN-475,486, 494 & 497)
- Interoperability testing
- Regression testing
- CONN-462, 483 & 510
- Adapter Update to Support Testing
- Multiple event codes for Query for Documents (CONN-478)
- Installation testing
- Completed the Healtheway Pilot
- Including some rerun of updated test cases
- Continued working on additional test cases for Healtheway certification (CONN-496)
Prioritized JIRA Planning Board of Committed User Stories for Sprint 111
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
...