April 22th - May 5th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points to the sprint with a total of 13.5 points. The team completed 13 points
...
- Sprint 106 review notes\- Notes about the work completed in s106. (Also includes work planned for s107)
- Sprint 106 planning notes - Notes about the work planned in s106. (Also includes work completed for s105)
- Sprint 106 code tag
- JIRA. See Sprint 106