Executive Summary

Overall Status

Info

Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint.

Burndown

Cumulative Flow

Sprint Themes

The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points to the sprint with a total of 13.5 points. The team completed 13 points

...