Sprint Review + Planning | Sep 23rd | 10am - 12pm ET

Registration for webinar: Click link below to register, and receive dial-in and Web participation details: 

https://attendee.gotowebinar.com/register/7556627107749161728

Sep 23 - Oct 7, 2013

Sprint Themes

Executive Summary

Overall Status

Info

Sprint status is excellent. The Product team

...

completed 19 out of the 21 story points this sprint.

Burndown

Image Added

Sprint Themes:

  • Support community with Release 4.2 deployments 
    • Several active community installations underway
  • Meaningful Use certification testing support (NIST)
    • Support of NIST testing effort
    • Work with current version of NIST test suite in CONNECT env.
    • Supported CMS with their 4.2 esMD installation(CONN-605,CONN-606)
  • Begin Direct Updates
    • Document and validate requirements for QoS and Trust Bundles (CONN-607)
    • Install the current version of RI in our development env.(CONN-608)
  • Finalize Audit Design Approach Approach (CONN-334)
  • Regression automation(CONN-583,CONN-610, CONN-625)
  • Start deeper research of potential issues identified in the Fortify security scan results(CONN-611 -- not completed)
  • Community Tickets
    • CONN-340

Prioritized JIRA Planning Board of Committed User Stories for Sprint 117

(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)

Image RemovedImage Added