Tip |
---|
Sprint Review + Planning | April 22th | 10am - 12pm ETRegistration for webinar: Click link below to register, and receive dial-in and Web participation details:https://attendee.gotowebinar.com/register/7556627107749161728 |
April 22th - May 5th, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status was excellent. The team accomplished all of the thematic work defined for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 106 comprising 11 points. The team added 2.5 points .
...
to the sprint with a total of 13.5 points. The team completed 13 points
- Continued Testing for Java 6 & Java 7 Support
- Installation testing on WAS 7 /IBM SDK 1.6
- Installation testing on WL 11g / JDK 1.6 (CONN-383/CONN-384)
- Installation testing on WL 12c / JDK 1.7 (CONN-371)
- Installation testing on WAS 8.5 /IBM SDK 1.7 (CONN-370)
- Installation testing on JBoss 7.1.1 /JDK 1.7 (CONN-368)
- Installation testing on GlassFish 3.1.2 /JDK 1.7 (CONN-369)
- Smoke test on all installations
- Documentation (CONN-375)
- Research and Write Design Approach for Multi-Specification Identification for QD/RD (Initiating)
- Review Responding design approach with technical leads from Federal Partners (conference call)
- Initiating design approach -
- HealtheWay certification pilot testing (system set up and smoke tests)
...
- CONN-317 Pre-test and smoke test for pilot https://developer.connectopensource.org/display/CONNECTWIKI/Table+1+-+Test+Cases+%28subset%29
JIRA Planning Board
...
for Sprint
...
106
Related Files
- Sprint 106 review notes\- Notes about the work completed in s106. (Also includes work planned for s107)
- Sprint 106 planning notes\ - Notes about the work planned in s106. (Also includes work completed for s105)
- Sprint 106 code tag
- JIRA. See Sprint 106