Tip |
---|
Sprint Review + Planning | April 8th | 10am - 12pm ETRegistration for webinar: Click link below to register, and receive dial-in and Web participation details:https://attendee.gotowebinar.com/register/7556627107749161728 |
April 8th - April 21st, 2013
Executive Summary
Overall Status
Info |
---|
Sprint status is good. The team encountered some unplanned infrastructure maintenance that impacted completion of all themes identified for the sprint. |
Burndown
Cumulative Flow
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 105 comprising 15.5 points. 0.5 points were added(CONN-367) and 3 points(CONN-317) were moved out as the team had to address some infrastructure maintenance tasks that were higher priority. The points committed were 13. The team completed 8 out of the total 13 points committed for the sprint.
- 4.1 Release
- Binaries and source available
- Complete and finalize supporting documentationCONNECT 4.1 released on April 10 2013 – Release overview page – CONNECT 4.1 Overview
- JBoss Application Server Support
- Continuous Integration and Code Base Improvements --Significantly increased automated test case coverage and build process
- Additional Improvements --For important issues resolution, see Release Notes for details
- CONN-355/357 – CONNECT not sending organization-id attribute statement in SAML header – necessary for certification testing
- Note - Support for CONNECT 4.0 is deprecated - all users are encouraged to target 4.1 for new adoption and upgrades.
- 4.2 Release
- Java 6 Support
- CONN-363 – Update codebase to use Java 6
- CONN-365 – Push CONNECT libraries built with Java 6 to maven central
- Design for QD and RD multi-spec enhancement related to specification version identification
- CONN-46 & CONN-15-293 - Link to design approach - Approach for enhancing multi-spec support(responding)
- Java 6 Support
- Participation in the Healtheway Certification pilot
- Partner and Community Support
Prioritized JIRA Planning Board of Committed User Stories for Sprint 105
Related Files
- Sprint 105 review notes\ - Notes about the work completed in s105. (Also includes work planned for s106)
- Sprint 105 planning notes - Notes about the work planned in s105. (Also includes work completed for s104)
- Sprint 105 code tag
- JIRA. See Sprint 105