February 19th - March 5th

Summary

Sprint status is excellent. All tasks have been completedmixed. GFE migration to an AWS environment has been more complex than originally estimated. Resolving unanticipated issues has delayed full migration by an estimate of a full two-week sprint.

Burndown:

Image RemovedImage Added

JIRA Planning Board of Completed User Stories:

Image RemovedImage Added