Sprint 36 Progress Summary
Sprint 36 Progress Summary
February 19th - March 5th
Summary
Sprint status is mixed. GFE migration to an AWS environment has been more complex than originally estimated. Resolving unanticipated issues has delayed full migration by an estimate of a full two-week sprint.
Burndown:
JIRA Planning Board of Completed User Stories:
Related Files:
Product Managers Meeting Presentation slide deck
Sprint code tag
Common-Types source
CONNECT-Webservices source
, multiple selections available,