Executive Summary
Overall Status
Info |
---|
Sprint status is good. The team accomplished all of the thematic work defined for the sprint. |
Sprint Themes
The Product team pointed and prioritized the following themes and tasks for Sprint 110 comprising 16 points. The team completed 15 points.
Burndown
Cumulative Flow
Sprint Themes
- Multi-Specification Identification for QD/RD
- Complete any remaining QA for both responding and initiating Multi-specification identification. (CONN-437, CONN-455)
- Ensure all unit testing from Pilot and Feature tickets are incorporated into regression and validation suites
- Release 4.2 testing plan dicussions and begin setting up necessary infrastructure (CONN-476)
- Continue working with Healtheway certification test cases (Table 2) and address any findings (CONN-472, CONN-394,CONN-395, CONN-396)
- Continue working on CI tickets and automated testing improvements (CONN-473,CONN-363,CONN-358)
Prioritized JIRA Planning Board of Committed User Stories for Sprint 110
(https://issues.connectopensource.org/secure/VersionBoard.jspa?selectedProjectId=10140)
Related Files
- Sprint 110 review notes - Notes about the work completed in s110. (Also includes work planned for s111)
- Sprint 110 planning notes - Notes about the work planned in s110. (Also includes work completed for s109)
- Sprint 110 code tag
- JIRA. See Sprint 110