May 18th - June 1st
Sprint 158 Themes
• X12 Auditing Development, Integration and Testing
– Development cleanup and address any testing findings
– Complete remaining testing both Batch & Real-time
– Schedule demonstration to CMS & Complete Documentation
• Closeout the Remaining Tasks Incorporating Automated Direct Testing in Regression Suite and CI processes
– Execute all Happy Path tests in an automated manner
– Resolve issues with automating negative test cases
• Complete Gateway property elements/attributes clean-up
– Final clean-up of adapter properties
– Update documentation
• Technical Stories
– Migrate old Universal Client Code to Plugin
– Deploy CONNECT of WebLogic 12.1.3
– Address additional Fortify scan findings
The team completed 17 points this sprint. Auditing of X12 service transactions is development complete.