Sprint 158 Themes

 • X12 Auditing Development, Integration and Testing
–  Development cleanup and address any testing findings
–  Complete remaining testing both Batch & Real-time
–  Schedule demonstration to CMS & Complete Documentation
 • Closeout the Remaining Tasks Incorporating Automated Direct Testing in Regression Suite and CI processes
–  Execute all Happy Path tests in an automated manner
–  Resolve issues with automating negative test cases
 • Complete Gateway property elements/attributes clean-up
–  Final clean-up of adapter properties
–  Update documentation
 • Technical Stories
–  Migrate old Universal Client Code to Plugin
–  Deploy CONNECT of WebLogic 12.1.3
–  Address additional Fortify scan findings

The team completed 17 points this sprint. Auditing of X12 service transactions is development complete. 