Sprint 174 Progress Summary

Sprint 174 Progress Summary

Dec 28th - Jan 11th

Sprint status is good. The team continued to support the federal agencies with their 4.5 testing. The team has started working on security scans/execution and making progress on the fixes and mitigation. Sprint review summary presentation is here.

Burndown:

Sprint Themes and related tickets for Sprint 174:

Development:

  • Audit logging and viewer
    • Fixed bugs on Audit viewer/logging 
  • Security testing
    • Installed Fortify and executed reports on codebase
    • Installed SonarQube and executed scans 
    • Fixed preliminary set of issues.
  • eHealth Exchange Product certification
    • CONNECT is now recognized as an eHealth Exchange Validated System
  • Support tickets
    • SSA support -  CONN-1625 - Getting issue details... STATUS
    • DoD support -  CONN-1632 - Getting issue details... STATUS

JIRA Planning Board of Committed User Stories for Sprint 174:

Related Files for Sprint 174:

Sprint 174 code tag 

Common-Types source

CONNECT-Webservices source

Related content

Sprint 172 Progress Summary
Sprint 172 Progress Summary
More like this
Sprint 164 Progress Summary
Sprint 164 Progress Summary
More like this
Sprint 176 Progress Summary
Sprint 176 Progress Summary
More like this
Sprint 148 Progress Summary
Sprint 148 Progress Summary
More like this
Sprint 173 Progress Summary
Sprint 173 Progress Summary
More like this
Sprint 147 Progress Summary
Sprint 147 Progress Summary
More like this