Jun 16 - June 30, 2014

Executive Summary

Overall Status

The Product team prioritized the following themes and tasks for Sprint 134 comprising 34 points. Sprint status is fine and the team completed all the tasks for the themes this sprint .  These themes included -   

 THEME 1 – Complete Direct development from a Config services integration on all app servers and implementing the base framework for message monitoring

THEME 2- Complete consolidating look and feel for all Admin GUI pages including Direct Config GUI

THEME 3 – Continue to work with CMS to come to  a common understanding of what will be delivered and understand clearly the expectations

In addition to the rest of the themes described above the Product Team will continue its support of the community(Tiani/INHS), ongoing support for VA on their 4.2.1 upgrade, work with OHT and Healtheway product certification testing.

The team completed 18 task oriented tickets totaling 34 points this sprint

Burndown


 

Sprint Themes and related tickets for Sprint 134:

JIRA Planning Board of Committed User Stories for Sprint 133:

 