July 14th - July 28th
Executive Summary
Overall Status
The Product team prioritized the following themes and tasks for Sprint 136 comprising 20 points. During the sprint there was a ticket(CONN-1265) that was pulled in to fix a known issue with the sprint tag build and 1 ticket was pulled out to accommodate the new tickets(CONN-1256/CONN-1268). Sprint status is good and the team completed 18 points this sprint. One ticket for 2 points remained at the end of the sprint and placed back into the backlog. These themes included -
1) Admin GUI (Testing and Cleanup)
2) Sprint 135 build issue.
3) X12 support (Continued discussion and review of requirements)
Burndown
Sprint Themes and related tickets for Sprint 136:
Community Implementation support
- Responded to forum posts - http://www.connectopensource.org/developer-resources/forums
- Support VA with 4.2.2.1 upgrade (CONN-1232)
- Several meetings throughout the sprint both phone and email correspondence
- Reviewed the values in VA UDDI file, researched and edited the values with the corrected entries
- Worked through a separate UDDI entry with the implementation team, determined to be a Healtheway data issue
- Helped work through a DR endpoint issue with one of their testing partners
- Merlin Crypto package classes read their related properties files from the bundled Properties.jar library; not the "config/nhin" folder
- Provided guidance on an IO error, helped to configure the correct URL with the correct port
- eHealth Exchange Product testing - Added test patient data to test files(CONN-1217)
Next Release (4.4)
- Admin GUI
- Integrating Administrative GUI pages with the back end configuration services
- Completed integrating the Direct configuration services for Domain set up(CONN-1200)
- CONN-1264 added to backlog
- Completed integrating the Direct services for Anchor set up(CONN-1201)
- CONN-1266 will be addressed in S136
- Completed integrating the Direct services for Certificates set up(CONN-1203)
- CONN-1265 will be addressed in S136
- Completed integrating the Direct services for Agent Settings set up(CONN-1204)
- Completed integrating the Direct services for Trust Bundles set up(CONN-1205)
- Fix Admin GUI sidebar UI/scrolling issues.(CONN-1216 and supporting tasks)
- Completed integrating the Direct configuration services for Domain set up(CONN-1200)
- Integrating Administrative GUI pages with the back end configuration services
Support for NwHIN CAQH Core X12 Document submission service
- Continue to review specifications.
- Updated requirements page - Support for X12 messaging(Draft)
- Draft story plan for 278 to discuss our understanding with CMS - 278 Story Plan(Draft)
- Need further discussion on WSDL definitions - See wiki page CONN-1167
JIRA Planning Board of Committed User Stories for Sprint 135:
Related Files
Sprint 135 code tag